Building up the foundation

The concrete slab is prepared and ready for the block-work.

First Fix Complete

With all the first fix electrical and plumbing complete the whole house is boarded.

Timber Frame

The new timber frame for plot 9 is built in situ.  The stick build will take about 5 weeks and will include easi-joists and attic trusses.

Foundations

Plot 35 & 35a foundations are laid and prepared for timber frame.  After excavation a stone bed is levelled and rolled into the ground.  Steel mesh sheets are tied in place on top of a polythene membrane.  Wooden shutters are constructed to hold the concrete in shape while being pumped into the new footing.

img_4935

Foundations

The new executive home is set on a raft foundation designed and prepared to take a timber frame structure.